TM 9-2350-222-10-2
OPERATE BOOM (PERFORM HOISTING) - Continued
CAUTION
Cable (C) must be kept tight and coils close together
when rewinding cable on winch (G).
5. Move WIN CH CONTROL lever (B) up to reel in cable (C) and lift
load (D). Release lever when load is at desired height.
NOTE
vehicle to place load (D) in desired position.
6. Move WINCH CONTROL lever (B) down to pay out cable (C) and
lower load (D). Release lever when load is placed in desired
position.
7. Remove lifting hook (E) from load (D).
8. Remove rope (F) from load (D).
9. Return rope (F).
TA132436
2-296