TM 9-4120-388-14
b. Removal
a. Inspection
This task covers:
c. Installation
INITIAL SETUP:
Equipment Condition
Junction box removed (4-46).
Side access cover removed (4-22).
Inspection.
a.
(1) Check for general condition and signs of leakage. If leakage is suspected, leak test per paragraph 5-10.
(2) Be sure that mounting hardware is secure.
b. Removal.
(1) Discharge the refrigeration system in accordance with paragraph 5-7.
(2) Remove two screws and Iockwashers from receiver bracket.
(3) Remove receiver bracket.
(4) Purge the system with nitrogen and debraze the tube connections. (See para 5-8 and 5-9.)
(5) Remove the receiver.
Installation.
c.
(1) Place the receiver on the tube ends, purge the system with nitrogen, and braze the tube joints. (See para
(2) Secure the receiver bracket to the casing side panel with two screws and Iockwashers.
(4) Leak test all newly connected joints and those in the repair area. (See para 5-10.)
(6) Evacuate and charge the refrigerant system. (See para 5-11 and 5-12.)
(7) Install junction box and lower panel. (See para 4-46.)