3-4. SERVICE UPON RECEIPT OF MATERIAL. (Cont)
(1) Remove the shipping container by cutting the metal bands that hold the top and sides of the
container to the base. Lift the container vertically and remove it from the base and cabinet.
(2) Remove the cushioning around the top of the cabinet and retain, if reuse is anticipated. Remove
the preservation barrier by tearing around the bottom of the cabinet. Remove the technical
publications envelope and accessory sack that are taped to the cabinet and put them in a safe
place.
DO NOT LIFT without holding unit in upright position.
Otherwise, unit will fall over causing injury to personnel.
Do not allow unit to swing while suspended from a lifting device.
Failure to observe warning may result in injury to personnel and
damage to equipment.
CAUTION
Use care in handling to avoid damage to the air conditioner. If an
overhead lifting device must be used, use an appropriate sling so that
the weight of the unit is borne by the base of the shipping container.
NOTE
The bolts used to anchor the cabinet base to the tiedown bars may be
used to anchor it in place in the installed location if the installation
method allows for anchoring from beneath.
(3) Attach an overhead hoist with an appropriate sling and spreader bar to the lifting rings
provided at each side of the cabinet. Raise the cabinet and remove the four carriage bolt
assemblies that hold the tiedown bars to the pallet from the underside of the pallet. Remove the
four bolts that hold the two tiedown bars to the unit base. Remove and retain the pallet and
carriage bolt assemblies and the tiedown bars and bolts, if reuse is anticipated. Be sure to remove
all remaining barrier material from the underside of the cabinet base. Lower the cabinet to the
floor in the desired position and remove the sling and hoist.
NOTE
It is recommended that the cabinet be left bolted to the shipping
pallet until time to place it in the installation position. All
receiving inspection actions can be conducted without removal from
the pallet.
c. Receiving Inspection. Perform receiving inspection of the air conditioner in the following manner:
(1) Inspect the equipment for damage incurred during shipment. If the equipment has been damaged,
report the damage on SF 364, Report of Discrepancy.
(2) Check the equipment against the packing slip to see if the shipment is compete. Report all
discrepancies in accordance with the instructions of DA Pam 738-750 (The Army Maintenance
Management System).