6. Connect the outlet line (figure 3 item 1) to the outlet fitting (figure 3, item 2).
7. Route the wiring to the junction box (figure 1, item 3), and connect the wiring using the marks and labels from
step 4 in Removal as a guide. Remove the labels.
8. Install the junction box cover (figure 1, item 2).
9. Remove the lockouts and tagouts (FM 55-502).
10. Perform a fresh water flush (WP 0005 00) to verify operation of the fresh water flush pump.
11. Check the fresh water flush pump for leaks and proper operation.
12. Return the equipment to the desired readiness condition.
END OF WORK PACKAGE
0019 00-4