TM 9-2330-211-14&P
AXLE AND SHACKLE BOXES
5-11.
This Task Covers:
Inspection and Replacement
a.
Removal
d.
e.
b.
Disassembly
Assembly
f.
c.
Cleaning
Installation
Initial Setup:
Tools/Test Equipment:
Equipment Conditions:
Hammer, sledge
Handle, socket wrench, 18 in., in. drive
Materials/Parts:
Hoist, with lifting sling, 5 ton
Pipe, 1 in. ID, 30 in.
Socket,
in., in. drive
Socket, 1 in., in. drive
References: TM 9-237
Torch outfit, cutting and welding
Trestle, motor vehicle maintenance, 10 ton (two
Personnel Required: Two
required)
Wrench, open-end,
in.
ACTION
ITEM
LOCATION
REMARKS
REMOVAL
1.
Tandem axle
Two walking beams (1)
Attach lifting sling to walking beams (1) and secure
assembly (10)
sling to hoist.
2.
Two access covers
Four U-bolts (4),
Using 1 in. socket, handle, and pipe, unscrew and
eight Iockwashers
take out.
(5 and 13)
(11), and nuts (12)
5-6