TM 9-4520-260-13
4-28. PACKAGING.
a. Place the thermostat, thermostat and power supply receptacles, repair parts, maintenance tools, and the
technical manual for the heater together in a close-fitting box conforming to PPP-B-636 domestic class. Place
each heater and box of consolidated components in a close fitting box conforming to PPP-B-636. Strap the
box.
b. Make sure the weight does not exceed the size limitations of the box specification.
4-29. ADMINISTRATIVE STORAGE.
a. Placement of equipment in administrative storage should be for short periods of time when a shortage of
maintenance effort exists. Items should be in mission readiness within 24 hours or within the time factors as
determined by the directing authority. During the storage period, appropriate maintenance records will be kept.
b. Before placing the equipment in administrative storage, current preventive maintenance checks and services
should be completed shortcomings and deficiencies should be corrected, and all Modification Work Orders
(MWO) shall be applied.
c. Storage site selection. Inside storage is preferred for items selected for administrative storage. If inside storage
is not available, trucks, vans, conex containers, and other containers may be used.
4-53/(4-54 blank)