(e) Set BATTERY CIRCUIT SELECTOR switch (S6, fig 2-2) to OFF.
(f) Set FIELD CIRCUIT switch (S32, fig 2-2) to REGULATOR
position. This will give regulated voltage, provided regulator has
been properly adjusted.
(g) Set MILLIVOLT METER MILLIVOLT DROP RANGE switch (S16, fig
(h) Apply specified load to generator, press MILLIVOLT METER
MILLIVOLT DROP PRESS TO READ switch S34, fig 2-1) and note millivolt
drop across contacts for a given load. (Refer to equipment manufac-
turer's test procedure. )
(i)
Perform other tests required by manufacturer's specifica-
tions.
( j ) Upon completion of tests, set MASTER LOAD DISCONNECT
Set FIELD CIRCUIT switch (S32, fig 2-2) to OFF.
(k)
(25) Reduce varidrive speed to one-quarter speed by turning
SPEED CONTROL (fig 2-4) clockwise, and stop varidrive by pressing STOP
pushbutton switch (S2).
c. Testing Generator-Regulator (Positive Ground).
2-12, 2-16, 2-17, 2-18, 2-20, 2-21 ,
and 2-22.)
NOTE
This test procedure is only a typical procedure.
(1) Position test stand controls in accordance with table 2-1.
(2) Install regulator on regulator mounting bracket located on
the right hand corner of test stand, and adjust to desired position.
(3) Install batteries in battery compartment (4, fig 4-3) of
test stand, and connect to proper binding posts on terminal board as-
(4) Set BATTERY CIRCUIT SELECTOR switch (S6, fig 2-2) to the
proper voltage for system under test.
(5) Set DC VOLTMETER OUTPUT VOLTAGE SELECT switch (S11, fig 2-1)
to BAT. Set MASTER LOAD DISCONNECT switch (S8, fig 2-2) to ON posi-
tion. Make certain that battery voltage is same as volts e of system
under test. Then, set BATTERY CIRCUIT SELECTOR switch (S6)to OFF,
and set DC VOLTMETER OUTPUT VOLTAGE SELECT switch (S11, fig 2-1) to
RECT GEN position. Place MASTER LOAD DISCONNECT switch (S 8, fig 2-2)
to OFF position.