TM 9-4910-663-12
(1) All jaw-type starters with a 5-inch bolt circle are mounted
by use of the chain mounting assembly (7, fig 2-10).
(2) All pinion-type starters with SAE mount are mounted by use
of the starter mounting bracket (43, fig 2-7).
(3) For starters with lever actuated start switches it will be
necessary to mechanically hold the switches in the ON position.
Figure 2-11 shows arrangements for
activating these lever actuated
start switches.
(4) After the above mounting procedures go to para 2-5 for
operation of the test stand.
Mounting of Rectifiers.
d.
(1) Mount the rectifier assembly onto the rectifier mounting
bracket (36-, fig 2-7). Secure with the rectifier nuts.
(2) Install the mounted rectifier into the rectifier chamber (6,
fig 4-3) being certain that the
rectifier plates are
parallel to the
flow of cooling air.
(3) After electrical connections are made (fig 2-19), close
rectifier chamber (6) door.
(4)After the above mounting procedures go to para 2-5 for
operation of the test stand.
e. Mounting Regulators (fig 2-7). All regulators and/or control
boxes are mounted onto the voltage regulator mounting bracket (35).
(1) Certain control boxes are mounted onto a control box mount-
ing plate (31) or regulator mounting plate assembly (33) which in turn
is mounted onto the multi-angle positioner (29) on the regulator
mounting bracket (35).
(2) The regulator mounting bracket (35) is adjustable vertically
to allow for ease in testing and may also be swung around the front
right corner of the test stand.
(3) It is also possible to adjust the voltage regulator in
either of two planes to simulate its actual vehicular mount.
(4) After the above mounting procedures, go to para 2-5 for
operation of the test stand.
2-5. GENERAL OPERATION OF TEST STAND. The following paragraphs
contain the general operating procedures for the test stand.
Change 1
2-26