TM 55-1925-282-14&P
0021 00
5. Label and disconnect the wires, and remove the cabling (figure 1, item 4) from the junction box (figure 1,
item 3) of the applicable high pressure pump.
6. Slowly, loosen the clamp (figure 1, item 5) to the low pressure hose (figure 1, item 6) until water begins to
drain from the fitting.
7. Allow any pressure to vent, or any fluid to drain.
8. Remove the low pressure hose (figure 1, item 6) from the low pressure fitting (figure 1, item 7).
9. Remove the low pressure fitting (figure 1, item 7) from the high pressure pump (figure 1, item 8).
10. Remove the high pressure hose (figure 1, item 9) from the high pressure fitting (figure 1, item 10).
11. Remove the high pressure fitting (figure 1, item 10) from the high pressure pump (figure 1, item 8).
12. Remove four bolts (figure 1, item 11), four nuts (figure 1, item 12), eight flat washers (figure 1, item 13) and
four lockwashers (figure 1, item 14) that secure the high pressure pump (figure 1, item 8) to its mounting
plate (figure 1, item 15), and remove the high pressure pump.
13. Discard the lockwashers.
INSTALLATION
1. Place the high pressure pump (figure 1, item 8) on the mounting plate (figure 1, item 15), and secure it in
place with four bolts (figure 1, item 11), eight flat washers (figure 1, item 13), four new lockwashers (figure 1,
item 14) and four nuts (figure 1, item 12).
2. Install the high pressure fitting (figure 1, item 10) into the high pressure pump (figure 1, item 8).
3. Install the low pressure fitting (figure 1, item 7) into the high pressure pump (figure 1, item 8).
4. Install the low pressure hose (figure 1, item 6), and secure it in place with the clamp (figure 1, item 5).
5. Install the high pressure hose (figure 1, item 9).
6. Install the cable (figure 1, item 4) and connect the wiring using the marks and labels from step 5 of Removal
as a guide.
7. Install the junction box cover (figure 1, item 2), and secure it in place with four screws (figure 1, item 1).
9. Remove the lockouts and tagouts (FM 55-502).
10. Perform the startup (WP 0005 00) on the applicable ROWPU, and check for leaks in the area of the high
pressure pump (figure 1, item 8).
11. Verify proper operation of the high pressure pump (figure 1, item 8). Ensure there are no unusual noises or
vibration, and that the ROWPU operates at proper system pressure.
12. Return the equipment to the desired readiness condition.
END OF WORK PACKAGE
0021 021304 -3lank