TM 9-2320-279-10-2
PMCS Tables (Cont)
Table 2-6. M964E1 Operator/Crew
Preventive Maintenance Checks and Services (Cont)
NOTE: Within designated interval, these checks are to be performed in the order listed.
B-Before Operation D-During Operation A-After Operation W-Weekly M-Monthly
Item to be Inspected
Equipment is
Procedure: Check for and have repaired, filled,
not ready/
or adjusted as needed
available if:
MATERIAL HANDLING CRANE (CONT)
(4) Move O/R EXT lever (1) to OUT posi-
Outrigger
tion until right outrigger beam (4) is
beam does
completely out.
not come
out.
(5) Move O/R EXT lever (2) to OUT posi-
Outrigger
tion until left outrigger beam (5) is
beam does
completely out.
not come
out.
One retain-
Check that two retaining pins are at-
ing pin
tached to each outrigger pad.
missing
from either
pad.
Change 3