4-21. OUTRIGGER RELAY BOX REPLACEMENT.
This Task Covers:
a. Removal
b. Installation
Initial Setup:
Equipment Conditions:
Materials/Parts:
Four lockwashers
Outrigger control panel power switch in OFF position.
Tools/Test Equipment:
General mechanic's tool kit
a.
REMOVAL
1.
Disconnect three cables from three connectors
(5).
2.
washers (2), and outrigger relay box (6) from
bracket (1). Discard lockwashers.
3.
If bracket (1) is damaged, remove additional
bolts, lockwashers, washers, and bracket from
semitrailer. Discard lockwashers.
b.
INSTALLATION
1.
If removed, install bracket (1) with washers,
new lockwashers, and bolts.
2.
Install outrigger relay box (6) with four washers
3.
Connect three cables to three connectors (5).
FOLLOW-ON TASKS: