TM 9-2330-381-14
2.
Aline valve handle (1) such that valve handle (1) is parallel between two ball valves (4) and push two valves (1)
into valve handle (2).
FOLLOW-ON MAINTENANCE
1.
Ensure suspension isolation valve assembly is installed and hydraulic lines and fittings are reconnected to valve
2.
Operate suspension isolation valve handle and check for proper operation (para. 2-6).
4-83.
SUSPENSION SHUT-OFF VALVE ASSEMBLY
This task covers:
a. Removal
b. Inspection
c.
Installation
INITIAL SETUP
Tools
Suspension isolation valve handle extension, item 1, appx. B
General mechanics tool kit, item 16, appx. B
The following tools can be found in common tool kit no. 1, item 17, appx. B:
Drain pan, 4 gl
Goggles, industrial
Extension light, 24 ft
Gloves, chemical and oil protective
Wrench, 1-1/4" combination
Degreaser tank, 20 gl
Creeper, mechanics
Materials/Parts
Cleaning compound solvent, item 25, appx. E
Lockwasher (6)
Locknut (5)
Preformed packing (10)
Lockwasher (5)
Personnel Required: 2
Equipment Condition
4-401