2-17 OPERATION (CONT).
b. Loading Semitrailer (Bulk Cargo)
(1) Install two panel Splice stakes (1) in sill holes at bulkhead. Guide top
of stake under top of wing panel.
(2) Install all 14 side racks (2).
(3) Install 12 panel splice stakes (3)
between the 14 side racks.
(4) Install two rear corner stakes (4).
(5) Install two rear racks (5) and panel
splice stake (6).
(6) Install quick release pins (7) at
bottom of racks.
(7) Install the four cross chains (8).
CAUTION
Install the four cross chains (8) before You load the
cargo. If chains are not installed, the stakes and racks
could bulge and break causing the cargo to spill.
(8) Load cargo into the semitrailer.