12. Remove floor jacks from rear axle (3) and front axle (2).
13. Remove trestles from frame rail (1).
OPERATIONAL CHECK
1.
Install tires (WP 0045 00, Tire Installation).
2.
After first three months of trailer operation, tighten self-locking nuts on U-bolts to 390-510 lb-ft
(530-690 Nm), in sequence increments of 50 lb-ft (68 Nm) in crisscross pattern.
END OF WORK PACKAGE