TM 9-4120-405-13&P
4-8. CHECKING UNPACKED EQUIPMENT. Perform receiving inspection of
the trailer-mounted, generator-set powered,
air conditioner in the following manner.
a. Inspec t the equipment for damage incurred during shipment. If the equipment has been damaged, report damage
on DD Form 6, Packaging Improvement Report.
b. Check the equipment against the packing slip to see if the shipment is complete. Report all discrepancies in
accordance with the instructions of DA Pamphlet 738-750, The Army Maintenance Management System.
NOTE
The following items may come packaged with this unit. However, they are not
used with this system.
Description
Part Number
Qty.
BOLT
MS90726-64
4
WASHER
13216E6138-2
4
SPACER
13216E6152
4
TUBE
13216E6153
4
MOUNT
13216E6137
8
CONNECTOR
13216E6177
1
CONNECTOR
13216E6209-1
1
CONNECTOR
MS3106R18-115
1
LOUVERS, SUPPLY
13216E6078
1
LOUVERS, RETURN
13216E6080-1
1
GUARD, FRESH AIR
13218E6956
1
c.
Check to see whether the equipment has been modified.
d. Using the packing list(s) removed in step a, inventory the accessories. Check missing items against shortage
packing list (if sent). Report any discrepancies to your supervisor.
e.
Remove all tags from components. Retain tags for future information.
f.
Store remaining accessories in the storage box.
4-9. INSTALLATION SITE PREPARATION.
a. Position trailer-mounted, generator-set powered, air conditioner so that rear end of trailer is on level ground and
air conditioner duct adapters are within 12 feet of shelter duct adapters. Refer to figure 4-2.
4-7