TM 9-4910-387-14-1
Section III. OPERATION UNDER USUAL CONDITIONS
2-10. INTRODUCTION
a. This section contains instructions for the procedures neces-
sary to operate the tester under usual conditions.
b. Recommended installation of the tester is in a protected area
that is well lighted, dust free, sound absorbing, and climate con-
trolled. Recommended room temperature is 72F (22C). This type
of facility will be the responsibility of the using organization.
2-11. PREPARATION FOR USE
WARNING
Shut off main power source when performing
maintenance.
a. Before the tester can be used, remove RH panel assembly
and perform the following procedures:
(1) Inspect fuel level by checking fuel level sight gage (1).
Remove cap (2) and fill as required with fuel (item 13,
app C).
(2) Inspect lube oil level by checking lube oil level sight gage
(3). Remove cap (4) and fill as required with lubricating oil
(item 11, app C).
(3) Drain contents of waste tank by opening valve (5) and
draining contents into an available minimum-size 3-gal.
(11.36-I) pan.
2-18