SHIPMENT AND LIMITED STORAGE AND DEMOLITION
TO PREVENT ENEMY USE
Section 1. SHIPMENT AND LIMITED STORAGE
52. Disassembly of
Equipment
(2) Disconnect the power cable con-
nector from the power cable stub
Perform the following procedures when
connector. Replace both connector
the AN/MSC-31 is moved to a different
covers.
location or placed in storage.
(3) Disconnect the power cable stub
a. Operate all ac power switches and
from the commercial source and
circuit breaker switches to their OFF
store it in storage cabinet No. 6.
positions except the LIGHT 1 and LIGHT
j. Disconnect the power cable from the
IN POWER 115V AC receptacle in the
1 LIGHTS, and the MAIN circuit breaker
power and signal entrance box and replace
switch.
the covers on the receptacle and connector.
b. Remove the batteries from the TA-
k. Disconnect the ground strap from the
312/PT, the SB-22(*)/PT, and the hand
GROUND TERMINAL in the power and sig-
lantern for prolonged storage or long-dis-
nal entrance box. Close and secure
tance shipment.
the cover on the power and signal entrance
c. Secure all components in their cases,
box.
mountings, or holders.
1. Store the ground strap in storage cab-
d. Place. all miscellaneous item in the
inet No. 1.
storage drawers and cabinets, and secure
m. Close and secure the covers on the ex-
the drawers and cabinets for transit.
haust blower vents and on the air filter.
e. Disconnect the field tires from the
n. Remove the ground rod and store it
PHONE and INTERCOM binding posts in
in the shelter (fig. 14).
the power and signal entrance box (fig. 8)
o. Wind the power cable on the cable
and from the SIGNAL 1 binding posts in the
reel and secure the reel to the floor of
f. Disconnect the. 26-pair cable at the
p. Recheck the area for any loose items.
power and signal entrance box and replace
Be sure that all items are properly stored
in the shelter.
nectors .
q. Clean t h e shelter thoroughly and
Note. The CX-4566\U is stored in its original
check to see that the drain plug is firmly
in place.
r. Close and lock the shelter door.
g. Operate the LIGHT 1 and LIGHT 2
switches, c i r c u i t breaker s w i t c h 1
LIGHTS, and the MAIN circuit breaker
switch to OFF.
The AN/MSC-31 can be transported by
h. If power was obtained from an adja-
cent shelter, disconnect the AN/MSC-31
15 for lifting, loading, and unloading in-
power cable from the OUT POWR 115V
structions.
AC receptacle at the adjacent shelter. Re-
place the receptacle and connector cover.
Caution: When transporting the AN/
i. If power was obtained from a com-
MSC-31 by air, the outside vent covers of
mercial source, proceed as follows:
the shelter must be opened to equalize the
(1) Turn off or disconnect the power.
pressure inside and outside the shelter.