TM 55-1925-286-13&P
0022 00
INSTALLATION
1. Wrap the male pipe threads of the gauge (figure 3, item 2) with antiseizing tape.
2. Thread the gauge (figure 3, item 2) into its piping (figure 3, item 3) and tighten snugly.
3. Open 1/4 turn ball valve (figure 3, item 1) to allow air flow to gauge.
4. Perform the Follow-On Service procedure at the end of this work package.
FOLLOW-ON SERVICE
1. Remove the lockouts and tagouts (FM 55-502).
2. CLOSE the drain valves as shown in table 1 on the starting air and ship's service air receivers.
4. As the compressors are running, check the system for leakage and for proper operation.
5. Return the equipment to the desired readiness condition.
END OF WORK PACKAGE
0022 022506 -5lank