FRAME 4
Using pole pike, push and hold upper part of pole (1) in position.
S o l d i e r A 1.
S o l d i e r B 2.
Using telegraph hand spoon, shovel 4 or 5 loads of dirt into hole (2)
and tamp with back fill tamp.
Repeat step 2 until hole is filled.
3.
Take pole pike away from pole (1).
S o l d i e r A 4.
Using telegraph hand spoon, pile the left over dirt around pole (1).
S o l d i e r B 5.
Using digging and tamping bar, tamp dirt around pole (1).
S o l d i e r A 6.
Operate rear winch (3) to put slack in winch cable (4). (Refer to
7.
par 4-15d.)
S o l d i e r B 8.
Take winch cable (4) from pole (1).
Pull in and secure outriggers (5). (Refer to para 4- 15i.)
9.