TM 9-2320-366-10-2
2-50. WRECKER MATERIAL HANDLING CRANE (MHC)
OPERATION (CONT)
j. Stow Outriggers and Shut Down MHC.
NOTE
Both outrigger pads are removed from outriggers the same way. Right
outrigger pad shown.
(1) Remove two pins (1) from outrigger pads (2).
NOTE
Operate LH O/R JACK lever and RH O/R JACK lever at the same time.
(2) Move LH O/R JACK lever (3) and RH O/R JACK lever (4) to UP position until
outriggers (5) are fully retracted.
(3) Install two pins (1) in outrigger pads (2).
(4) Stow two outrigger pads (2) in tool box.