TM 9-2330-227-14&P
SUBFRAME AND SUSPENSION ASSEMBLY (BOGIE) - CONTINUED
ACTION
REMARKS
ITEM
LOCATION
INSTALLATION
Attach chains from overhead hoist
Semitrailer
a.
6.
lifting eyes (1)
to lifting eyes.
Lift semitrailer off cribbing.
b.
Remove cribbing.
c.
Bogie
a.
Support with dolly jack, and roll
7.
assembly (11)
under semitrailer body.
b.
Position under semitrailer using
blocks as required.
Using overhead hoist, lower semitrailer,
Semitrailer
8.
but do not allow full weight to rest on
bogie assembly (11).
Two master
Move bogie assembly (11) until master
9. Two blocks (6),
pins (10) can be screwed in.
pins (10)
blocks (8), and
weld nuts (9)
Using overhead hoist, lower completely
Semitrailer
10.
onto bogie assembly (11).
Two remaining
Screw in, and tighten all four pins (10)
11. Two remaining blocks
master pins (10)
(6), blocks (8), and
handle with 3/4-inch drive.
weld nuts (9)
Place in position.
Four plates (2)
12. Four blocks (6)
Screw on, and tighten using 3/4-inch
Four nuts (3),
13. Four plates (2)
Iockwashers (4),
3/4-inch drive.
and washers (5)