Install two load binders (1), one on each side of trailer in lower length of tiedown chain (2)
20.
between lower portable bolster (3) and tiedown ring (4). Apply only enough tension to take up
slack in tiedown chain (2).
Apply tension to each of the four installed load binders (1) in increments, being careful not to
21.
shift load, until all tiedown chains (2) are tight.
Install three straps (5) over load and tighten and secure to tiedown rings (6).
22.
Inspect load for proper alinement and proper tiedown tension, and that no possibility of the
23.
load breaking loose during movement exists.
Secure all loose chain and strap ends.
24.