TM9-2330-358-14&P
NOTE
Mark location of float pad chain on frame before
beginning procedure.
(1) Using cutting torch, cut weldment.
(2) Grind weld off frame surface.
Figure 4-57. Float Pad
c. Chain Installation.
(1) Position float pad chain (5, fig. 4-57) on frame according to markings.
WARNING
Wear welding mask, gloves, and apron when welding or
using cutting torch. Failure to wear adequate -
protective clothing may result in serious injury.
(2) Weld float pad chain (5) to frame using arc welder.
Refer to TM 9-237.
(3) stow float pad (6).
d.
Handle Installation.
(1) Position handle (4, fig. 4-57) on float pad (6).
(2) Secure handle (4) with two bolts (3), washers (2) and nuts (l).
(3) Stow float pad (6).
TASK
ENDS
HERE
4-99