TM 9-2330- 371-14&P
LOWER TORQUE ROD
This task covers:
b. Cleaning, inspection, and repair
INITIAL SETUP
Personnel Required
Tools
One
Jack kit, hydraulic hand
Equipment Condition
(ports power)
Pliers, diagonal
Semitrailer parked on level ground with
Press, arbor
landing gear down, and wheels blocked.
Socket, torque rod (item 1,
Wrench, torque rod (item 2,
Materials/Parts
Brush, soft
Solvent, drycleaningr PD-680
ACTION
REMARKS
ITEM
LOCATION
NOTE
There are four lower torque rods on the semitrailer.
This procedure is for one. Repeat this procedure for
the others.
REMOVAL
Two cotter pins
Using pliers, take out.
Two nuts (1)
1.
(3) and (4)
and (2)
Using torque rod socket and handle, un-
Nut (1)
Torque rod (5)
2.
screw and take off.