TM 9-2350-222-10-2
OPERATE BOOM (PERFORM HOISTING) - Continued
1. Move WINCH CONTROL lever (B) down to pay out enough cable
(C) to reach load (D).
2. Connect lifting hook (E) to load (D).
3. Connect rope (F) to load (D).
4. Hold rope (F) to prevent load (D) from turning.
WARNING
Keep all personnel clear of winch cable during hoisting
operation. All personnel must be at least the length of
cable away from vehicle and load. Serious injury could
result if winch malfunctions or cable breaks.
CAUTION
Lifting capacity with a single line is 17,500 pounds.
TA132435
2-295