TM 9-2350-222-10-2
OPERATE BOOM (PERFORM HOISTING) - Continued
CAUTION
Cable (C) must be kept tight and coils close together
when rewinding cable on winch (Q).
20. Move WINCH CONTROL lever (B) up to reel in cable (C) and lift
load (N). Release lever when load is at desired height.
NOTE
vehicle to place load (N) in desired position.
21. Move WINCH CONTROL lever (B) down to pay out cable (C) and
lower load (N). Release lever when load is placed in desired
position.
22. Remove snatch block (D) from load (N).
23. Remove rope (P) from load (N).
24. Move WINCH CONTROL lever (B) down to pay out cable (C) and
lower snatch block (D). Release lever when snatch block rests on
the ground.
TA252758
Change 1
2-302