TM 9-4120-388-14
4-3. UNPACKING - Continued.
It is recommended that the cabinet be left bolted to the shipping pallet until time to place it
in the installation positon. All receiving inspection actions can be conducted without removal
from the pallet.
d.
Remove pallet. Attach an overhead hoist with an appropriate sling and spreader bar to the lifting handles pro-
vided at each side of the cabinet. Raise the cabinet and remove the four carriage bolt assemblies that hold the
tie down bars to the pallet from the underside of the pallet. Remove the four bolts that hold the two tie down
bars to the unit base. Remove and retain the pallet and carriage bolt assemblies and the tie down bars and bolts,
if reuse is anticipated. Be sure to remove all remaining barrier material from the underside of the cabinet base.
Lower the cabinet to the floor in the desired position and remove the sling and hoist.
NOTE
The bolts used to anchor the cabinet base to the tie down bars may be used to anchor it
in place in the installed location if the installation method allows for anchoring from beneath.
4-4. RECEIVING INSPECTION. Perform receiving inspection of the air conditioner in the following manner:
Inspect the equipment for damage incurred during shipment. If the equipment has been damaged, report the
a.
damage on DD Form 6, Packaging Improvement Plan.
b.
Check the equipment against the packing slip to see if the shipment is complete. Report all discrepancies in
accordance with the instructions of DA PAM 738-750, The Army Maintenance Management System (TAMMS).
c.
Check to see whether the equipment has been modified.