1. Wrap the male threads of the pipe fittings (figure 8, item 10) with four wraps of antiseizing tape.
2. Thread the pipe fittings (figure 8, item 10) into place on the product water diverter valve (figure 8, item 3), and
tighten snugly into place.
3. Position the product water diverter valve (figure 8, item 3) on its foundation (figure 8, item 9), and secure it in
place with four screws (figure 8, item 7) and four flat washers (figure 8, item 8).
4. Connect the tubing (figure 8, items 4, 5 and 6) to the product water diverter valve (figure 8, item 3).
5. Slide the wire plug (figure 8, item 2) onto the product water diverter valve (figure 8, item 3), and secure it in
place with the screw (figure 8, item 1).
6. CLOSE the flow control panel and tighten the two captive screws (figure 4, item 7).
7. Perform the Follow-On Service procedure at the end of this work package.
FOLLOW-ON SERVICE
1. Remove lockouts and tagouts (FM 55-502).
2. Start up the applicable ROWPU (WP 0005 00), and check for proper system operation.
3. Check the ROWPU for any leaks.
4. If the salinity probe was removed or replaced, perform the Calibrate Salinity Probe procedure contained in
this work package.
5. If the high pressure cutoff switch was removed or replaced, perform the Adjust High Pressure Switch Cutoff
procedure contained in this work package.
6. If the low pressure cutoff switch was removed or replaced, perform the Adjust Valve Misalignment Shutdown
Switch procedure contained in this work package.
7. If the valve misalignment shutdown switch was removed or replaced, perform the Adjust Valve Misalignment
Shutdown Switch procedure contained in this work package.
8. Return the equipment to the desired readiness condition.
END OF WORK PACKAGE