TM 55-1925-284-14&P
OPERATOR, UNIT, DIRECT SUPPORT, AND GENERAL SUPPORT MAINTENANCE
MARINE SANITATION DEVICE FOR
INLAND AND COASTAL LARGE TUG (LT)
OPERATION UNDER USUAL CONDITIONS
INITIAL SETUP:
Materials/Parts:
References:
Gloves, Chemical and Oil Protective (Item 1,
FM 55-502
TM 55-1925-273-10
Goggles, Industrial (Item 2, Table 3,
Personnel Required:
Equipment Conditions:
One Watercraft Engineer, 88L
All ventilation fans operating normally (TM 55-1925-
273-10)
SECURITY MEASURES FOR ELECTRONIC DATA
There are no required security measures for electronic data. The Marine Sanitation Device (MSD) components
do not use or store any electronic data.
OPERATION UNDER USUAL CONDITIONS
SYSTEM STARTUP
NOTE
The System Startup procedure is performed after the following: New System Instal-
lation, System Lay Up, System Overhaul, Air Scour and Pump Out of the Media
1. Set to ON the AUX MACH SPACE NO. 1 PWR PNL NO. 4 circuit breaker (figure 1, item 1) at the main
switchboard (figure 1, item 2) in the Enclosed Operating Space (EOS).
1
3
2
Figure 1. Main Switchboard Circuit Breakers
0005 00-1