TM 9-2330-227-14&P
TIRE AND WHEEL ASSEMBLY- CONTINUED
ACTION
LOCATION
ITEM
REMARKS
INSTALLATION - CONTINUED
NOTE
Lugbolts (7) are marked R. or L. in direction of forward wheel rotation. To tighten stud
nuts (6) on right side, turn clockwise. To tighten stud nuts (6) on left side, turn
counterclockwise.
9.
Six stud nuts (6)
Screw onto Iugbolts (7), and tighten in
the sequence shown using stud nut wrench.
10. Side of frame (3)
Axle (4)
Take trestles out from under axle (4).
a.
where tire and wheel
Lower jack until inner tire and wheel
b.
assembly is being
assembly (5) rests on the ground.
removed
11. Lugbolts (7)
Six stud nuts (6)
Using stud nut wrench, tighten as much as
possible in sequence shown below.
NOTE
Have Organizational Maintenance tighten stud nuts to 400 to 425 ft-lb (540-560 Nm) of
torque as soon as possible, with outer tire and wheel assembly removed.
12.
Axle (4)
Raise jack until inner tire and wheel
assembly (5) is off of ground.
TA231223
3-15