Landing Leg Installation.
h.
S e c u r e with bolt (7), washer (6) and
(2) Install coupling (4) on landing leg.
nut (5).
If installing coupling (12) on left landing leg, secure
with bolt (15), washer (14) and nut (13).
(3) Position landing leg (1, figure 4-45) and coupling on frame. Secure
landing leg (1) with eight bolts (3), sixteen flat washers (4) and eight
n u t s ( 5 ) . Torque nuts to 150-160 lb ft (204-218 Nm).
(4) Install bolt (3, figure 4-44), washer (2) and nut (1) on coupling (4).
Secure left landing leg coupling with bolt (11), washer
(10) and nut (9).
(5) Install braces (7 and 8, figure 4-45) and secure with four bolts (6), eight
flat washers (4) and four nuts (5). Torque brace nuts to 150-160 lb ft
(204-218 Nm).
i.
Gear
Box
Installation.
(2) Secure gear box (4) with four bolts (3), eight washers (2) and four nuts
( 1 ) . Torque nuts to 150-160 lb ft (204-218 Nm).
(3) Secure gear box coupling (9) with screw (8), washer (7) and nut (6).
j.
Crank
Installation.
(2) Secure crank (4) with bolt (3), washers (2) and nut (1).
(3) Install float pad in bracket.
(4) Crank down lower landing leg and grease per lubrication chart (figure 3-1).