TM 9-4110-255-14
This task covers: Testing
INITIAL SETUP
Equipment Conditions:
Refrigeration unit shut down (para 2-7) and battery
Right side door open.
Testing.
(1)
Unplug connection (1) from voltage regulator (2).
(2)
connection (1). Continuity should be indicated. If no continuity was indicated, notify direct support
maintenance.
(3)
frame. Continuity should not be indicated. If continuity was indicated, notify direct support maintenance.
(4)
If no failure was indicated, install connection (1) onto voltage regulator (2).
NOTE
FOLLOW-ON MAINTENANCE:
Close right side door.
Connect battery (para 4-35) and put unit back into service.
4-135