TM 9-4120-388-14
4-58. TERMINAL BOARDS (TB1 and TB2).
This task consists of: a. Inspection
b. Removal
c. Installation
INITIAL SET-UP:
Equipment Condition
Junction box cover removed (4-47).
Inspection.
a.
(1) Check terminal boards for loose or corroded terminals, cracks, and obvious damage. Replace if cracked
or broken.
(2) Be sure that wire leads are secure and properly located. (See Figure 4-16.)
b. Removal.
(1) Tag and disconnect wire leads.
(2) Remove four screws and nuts from terminal board (TB2).
(3) Remove four screws and flat washers from terminal board (TB1).
(4) Remove terminal boards.
Installation.
c.
(1)
Secure terminal board (TB1 ) with four screws and flat washers.
(2)
Secure terminal board (TB2) with four screws and nuts.
See tags and wiring diagram (Figure 4-16) and connect wire leads.
(3)
Remove tags.
(4)
Install junction box cover and lower front panel. (See para 4-47.)