TM 9-4120-395-14&P
5-21.
TUBING AND FITTINGS-Continued.
b.
Removal.
(1) Discharge the refrigeration system. See para 5-6.
(2) Remove tubing Insulation if required.
(3) Purge the system with nitrogen and debraze the tube connections. See paras 5-6 and 5-7.
(4) Remove the tubing.
c.
Installation.
(1) Align the replacement tubing.
(2) Purge the system with nitrogen and braze the tube joints. See paras 5-6 and 5-7.
(4) Leak test all newly connected joints and those in the repair area. See para 5-8.
(5) Evacuate and charge the refrigerant system. See paras 5-9 and 5-10.
(6) Replace tubing insulation as required.
(7) Install all panels and doors. See paras 4--17 and 4-19.
5-42