4-29. OUTRIGGER RELAY WIRING HARNESS REPLACEMENT.
This Task Covers:
a. Removal
b. Installation
Initial Setup:
Equipment Conditions:
Materials/Parts:
Tools/Test Equipment:
General mechanic's tool kit
a. REMOVAL
NOTE
All connectors and outrigger relay wiring harness should be tagged before removal.
All four outrigger connections are disconnected in the same way.
1.
Disconnect two connectors (1) from lower outrigger limit switch.
2.
Disconnect two connectors (3) from upper outrigger limit switch.
3.
Disconnect connector (2) from outrigger relay box.
4.
Repeat steps 1 through 3 for other three outriggers.
5.
Disconnect connector (4) from master relay wiring harness.
6.
Disconnect connector (5) from master relay box.
7.
Disconnect two connectors (6) from outrigger control box.
8.
Remove outrigger relay wiring harness (7) from semitrailer.
b.
INSTALLATION
1.
Install outrigger relay wiring harness (7) to semitrailer.
2.
Connect two connectors (6) as tagged, to outrigger control box.
3.
Connect connector (5) as tagged, to master relaybox.
4.
Connect connector (4) as tagged, to master relay wiring harness.
5.
Connect two connectors (3) as tagged, to upper outrigger limit switch.
6.
Connect connector (2) as tagged, to outrigger relay box.
4-48