TM 9-2330-381-14
2.
Install hitch pin (5) through davit base (2) and davit (6). Secure with linch pin (4).
3.
Operate winch assembly to lower hook (1). Rebook to stow position on davit base (2).
4-71. SNATCH BLOCK
This task covers:
a. Removal
c. Inspection
e. Installation
b. Disassembly
d. Assembly
INITIAL SETUP
Tools
General mechanics tool kit, item 16, appx. B
The following tools can be found in common tool kit no. 1, item 17, appx. B:
Degreaser tank, 20 gl
Hammer, 3 lb
Gloves, chemical and oil
Machinist's vise, 4"
protective
Soft-jawed vise caps
Goggles, industrial
Materials/Parts
Antiseize compound, item 3, appx. E
Cleaning compound solvent, item 25, appx. E
Locknut (2)
Cotter pin
Lockwasher
Cotter pin
Personnel Required: 2
4-333