m. Place TM 9-2330-381-14 and TM 9-2330-381-24P in plastic bags (item 1, table 4-1) and heat seal bags.
n. Prepare a wooden box (item 5, table 4-1) and place all items prepared and tagged in steps a thru m above, into
box. Place cardboard cushion (item 4, table 4-1) between layers of items as they are packed into box.
4-119. STOWAGE PROCEDURES
NOTE
These procedures apply to both Level A and Level B.
a. Load BII box (1) onto semitrailer platform. Position box on streetside of semitrailer just forward of bogie #2 and
inboard of the second and third tiedown rings (2). Secure BII box to platform deck with steel strapping (item 11,
table 4-1). Pass strapping (3) through the streetside and curbside tiedown rings (2).
Change 1 4-533