TM 55-1925-284-14&P
0016 00
4. Tighten the four bolts (figure 1, item 6).
5. Check the belt tension several times during the first 50 hours of operation. Adjust if necessary. Use the
Adjust Belt procedure of this work package for checking tension and adjusting the belt.
6. Position the belt guard (figure 1, item 4) over the studs (figure 1, item 3) on its base (figure 1, item 5) and
secure it with the four nuts (figure 1, item 1) and four new lockwashers (figure 1, item 2).
7. Perform the Follow-On Service procedure at the end of this work package.
FOLLOW-ON SERVICE
1. Remove the lockouts and tagouts (FM 55-502).
3. Check the blower for proper operation.
4. Return the equipment to the desired readiness condition.
END OF WORK PACKAGE
0016 016708 -7lank