TM 55-1925-284-14&P
UNIT MAINTENANCE
MARINE SANITATION DEVICE FOR
INLAND AND COASTAL LARGE TUG (LT)
BLOWER ASSEMBLY, BLOWER; REPLACE
INITIAL SETUP:
References (continued):
Tools and Special Tools:
TM 55-1925-273-10
Tool Kit, General Mechanic's (Item 1, Table 2,
Materials/Parts:
Dry Cleaning Solvent (Item 5, Table 1,
Gloves, Chemical and Oil Protective (Item 1,
Goggles, Industrial (Item 2, Table 3,
Equipment Conditions:
Set to OFF MSD DISCHARGE PUMP AND
BLOWER circuit breaker in 440V power panel
No. 4. Lock out and tag out (FM 55-502).
All ventilation fans operating normally (TM 55-1925-
273-10).
Personnel Required:
CLOSE valve CA-81 LP AIR SHUTOFF. Lock out
Two Watercraft Engineers, 88L
and tag out (FM 55-502).
References:
FM 55-502
TB 43-0218
WARNING
Never reuse locking hardware. Reuse of locking hardware such as lockwashers,
locking nuts, cotter pins, and lockwire can result in undetected loosening of fas-
tening hardware causing catastrophic component failure resulting in death, in-
jury, or damage to equipment. In accordance with TB 43-0218, ensure that all
locking hardware is discarded upon removal and replaced with new.
REMOVAL
! CAUTION
Failure to use two wrenches while loosening unions, fittings, valves and piping may
cause damage to the valves, piping, fittings and unions.
2. Disconnect the blower discharge piping (figure 1, item 1) at the union (figure 1, item 2).
3. Remove the discharge piping (figure 1, item 1) from the check valve (figure 1, item 3).
4. Remove the check valve (figure 1, item 3) from the tee fitting (figure 1, item 4).
5. Remove the relief valve (figure 1, item 5) from the tee fitting (figure 1, item 4).