TM 9-2330-381-14
4-60.
LOADING RAMP (CONT)
4.
Increase spring tension as follows:
a. Raise ramps and attach chain assemblies (2) to platform (para. 2-20).
b. One person must hold spring (12) in place while second person removes locknut (14) and capscrew (15) from
adjustment fitting (16).
c. Slide spring (12) and adjustment fitting (16) upward on rod (8) and aline adjustment fitting with next available hole
in rod (8). Install capscrew (15) and secure capscrew with locknut (14).
d. Operate ramps and check for proper tension on spring. Repeat steps 4a and 4b as required.
4-61.
APU FRAME
This task covers:
a. Removal
b. Installation
INITIAL SETUP
Tools
General mechanics tool kit, item 16, appx. B
Materials/Parts
Locknuts (2)
Locknuts (2)
Personnel Required: 2
Equipment Condition
4-302 Change 1