4.35 HEATER ELEMENTS -INSPECT/TEST/REPLACE. This task covers inspect, test, remove and install.
INITIAL SETUP
Test Equipment:
Materials/Parts:
Equipment Conditions:
Junction box pulled half way out of unit (paragraph 4.25)
Remarks
Action
Location/Item
Allow heating elements to cool for 15
minutes before touching.
Disconnect air conditioner power supply
before doing maintenance work on the
electrical system.
Heater
EIements and
EIectrical
Wiring
Inspect for damage to elements or leads.
a.
Inspection
b.
Replace damaged leads and bad elements.
c.
Heater Support
Bracket
a.
Inspection
Replace as necessary.
b.