TM 9-4120-378-14
4.31 TRANSFORMER. - Continued
Remarks
Action
Location/ltem
Test
a. Check for continuity across primary terminals 1
See fig. FO-2 for all test steps.
and 6.
b. Check for continuity across secondary terminals
7 and 8.
c. Check for discontinuity between primary and sec-
ondary coils.
replace.
e. Connect 115 Vac power source to primary termi-
nals.
g. Check for reading of 27 to 33 Vat.
h. If transformer fails test, replace.
a. Slide new shrink sleeving onto and up wire.
Installation
b. Solder leads on terminals and remove tags.
c. Slide shrink sleeving down wire and over solder
connection.
d. Heat-shrink sleeving onto solder connection.
(2) and Iockwasher (1).
f. Install junction box.
g. Install control module.
i.
Install front top cover.
4-79